8 February 2024 04:21 pm Views - 1553
The agreement pertains to the 100 MW Ground Mount Solar project located in Siyambalanduwa.
This endeavour, which has been in the pipeline since its advertisement by the CEB in September 2022, underwent thorough evaluation throughout 2023.
At the culmination of the evaluation process, Rividhanavi emerged as the lowest and successful bidder, clinching the project at the end of 2023.
In addition to the solar infrastructure, Rividhanavi (Pvt) Ltd. will undertake the construction of a 27.5 Km transmission line essential for the project's functionality. Upon completion, the transmission line will be transferred to the CEB, facilitating seamless integration into the national grid.
With an anticipated investment totaling USD 132 million, the consortium is poised to catalyze substantial progress in Sri Lanka's renewable energy sector.